No compensation obligation of the grid operator for feed-in management-related balancing energy costs (only available in german language)

"Infrastrukturrecht (IR) 1/2023, Seite 17f." [Infrastructure Law (IR) 1/2023, page 17f.]

11.01.2023

"The operator of an offshore wind farm who, on the basis of a contractual obligation to his direct marketer, assumes costs for balancing energy demanded by the latter, cannot demand reimbursement of these costs from the grid operator." 

Our expert Thorsten Kirch informs in this article about the decision of the Bayreuth Regional Court of 17.10.2022.

 Newsletter Icon

We inform you about current legal developments in the areas relevant to you.

Subscribe to our Newsletter

goep_0459_290622

Einige der von uns gesetzten Cookies dienen dazu, bestimmte Funktionen unserer Webseiten zu ermöglichen, insbesondere zur Steuerung des Cookie-Banners (damit dieses bei Ihren erneuten Besuchen nicht immer wieder angezeigt wird). Diese Cookies enthalten keine personenbezogenen Daten, insbesondere nicht Ihre IP-Adresse. Andere Cookies, die zu Analysezwecken gesetzt werden (siehe hierzu auch den Abschnitt „Web-Analyse-Tools“), helfen uns zu verstehen, wie Besucher mit unseren Webseiten interagieren. Diese Cookies dienen dazu, die Nutzung unserer Webseiten statistisch zu erfassen und zum Zwecke der Optimierung unseres Angebotes auszuwerten. Die Analyse-Cookies werden bis zu 13 Monate gespeichert.

Save Cancel OK Deny tracking Privacy policy